17. IVV Plan¶
Document status:
- initial
- verified
- published
Elements needed to integrate, verify and validate the system. (Integration plan, verification plan, validation plan, qualification plan)
17.1. IVV activities¶
- Planning
- pm1_16: Verify PP
- Project Control
- pm3_1: Evaluate Progress
- pm3_2: Address Risk
- pm3_3: Justify
- Requirements Engineering
- sr2_2: Verify StRS
- sr2_3: Validate StRS
- sr2_6: Verify SysRS and SERS
- sr2_7: Validate SysRS
- sr2_8: Update Traceability
- sr2_9: Update IVV
- Architecture
- sr3_2: Functional trade-offs
- sr3_4: Physical trade-offs
- sr3_5: Verify System Design
- sr3_6: Update IVV
- sr3_8: Verify System Manual
- Construction
- sr4_3: Verify System
- IVV
- sr5_1: Verify IVV plan and procedures
- sr5_2: Integrate System
- sr5_3: Verify System
- sr5_4: Validate System
- sr5_7: Verify Operation Guide
- Delivery
- sr6_1: Review Product
- sr6_4: V&V Maintenance and Training
- sr6_6: Transition to Manufacturing and support
17.2. Integration Strategy¶
TBD: integration strategy regarding the System Elements Requirements and interfaces.
17.3. Environmental constraints¶
None.
17.4. IVV Requirements¶
None.
17.5. Special procedural requirements¶
None.